DC Interference Mitigation Project for Meishi Branch Pipeline & AC Interference Mitigation Projects for Huizhou, Guangzhou and Foshan

Construction Scheme: Zinc Band Drainage + New Cathodic Protection Station Construction + Project Acceptance Report
Construction Conclusion:One new cathodic protection station was built, and 8 sets of zinc band drainage groundbeds with a total length of 1900 meters were installed.

Add Surrounding‑Environment Diagram for New Cathodic Protection Station Construction
Drainage ground bed excavation
Cable Wiring Anti‑corrosion
Flow Queue Test
Installation of long‑term reference electrodes and test specimens
drilling construction
Anticorrosive coating inspection
Potentiostat Unit A operating at a constant current of 8 A
Curve of Off‑Potential for Test Stakes
Add Surrounding‑Environment Diagram for New Cathodic Protection Station Construction
Drainage ground bed excavation
Cable Wiring Anti‑corrosion
Flow Queue Test
Installation of long‑term reference electrodes and test specimens
drilling construction
Anticorrosive coating inspection
Potentiostat Unit A operating at a constant current of 8 A
Curve of Off‑Potential for Test Stakes

Project Introduction

Based on data from cathodic protection remote monitoring equipment, special stray current surveys and quarterly cathodic protection inspections, Guangdong Dapeng LNG Co., Ltd. found three under-protected sections with substandard cathodic protection potential on the Meishi Branch Pipeline. Four segments of the Huizhou Branch Pipeline had induced AC voltage exceeding 15 V, with a maximum value of 17.35 V. Three pipeline sections in Guangzhou and Shenzhen showed excessive AC current density. A 1 cm² corrosion coupon was buried for long-term monitoring (more than 15 days), followed by 24-hour continuous measurement. The average interference current density was 527 A/m², and the peak value reached 636 A/m². After on-site verification, construction works for DC interference mitigation on the Meishi Branch Pipeline and AC drainage remediation in Huizhou, Guangzhou and Shenzhen are required to reduce pipeline corrosion risks.

  • Project Name
    DC Interference Mitigation Project for Meishi Branch Pipeline & AC Interference Mitigation Projects for Huizhou, Guangzhou and Foshan
  • Installation Time
    July 03, 2024
  • Project Notes
    Shenzhen City, Guangdong Province